Capital Campaign Timeline 2015-2020

Capital Campaign Timeline

2020

  • Preliminary architectural plans reviewed by Board of Trustees, Church Council and congregation
  • Preliminary price tag (pre-architectural input) of $1.7 million

2019

  • Reviewed preliminary architectural plans, including expanded classroom, office and storage space, renovated kitchen, and an elevator.
  • Gathered bids from engineering firms to finalize the needs list and prioritize projects within allowable parameters.

2018

  • Kicked off Capital Campaign with Annual Stewardship Drive
  • Pledges ranged from 1- to 5-year commitments

2017

  • With consultant Andy Hamlin, Strategic Visioning Task Force proposed renovations, repairs and improvements to the church facility and grounds estimated at $1.7 million.
  • Aspirational goal of $1,100,000 set.


2016

2015